Please scroll down for English version.
2月28日10時50分,中國電力常熟發電百萬機組儲能調頻項目受電工作圓滿成功,標誌着該項目的最終投運已進入倒計時階段。
2月28日10時50分,中國電力常熟發電百萬機組儲能調頻項目受電工作圓滿成功,標誌着該項目的最終投運已進入倒計時階段。

作爲中國電力系統內首批儲能示範項目,常熟發電高度重視,積極配合項目建設方——新源智儲公司做好項目前期報備、施工過程協調、安全質量管理等工作,確保項目順利推進。目前,該項目已進入設備調試階段。
該儲能調頻項目自2021年9月份開始建設,總容量30MW/30MWh,預計於2022年3月底試運行。項目能較好提高機組的調頻輔助服務響應能力,補足火電機組調節響應的短板,幫助機組在輔助服務市場爭取效益。
Changshu Energy Storage and Frequency Regulation Project Has Been Energized
At 10:50 on February 28, 2022, the energy storage and frequency regulation project owned by Changshu Power Generation Company has been successfully energized, marking the countdown of final commissioning of the project.
As one of CPID's first energy storage demonstration projects, the project has been attached great importance by Changshu Power Generation Company, which has actively cooperated with the project builder (Xinyuan Smart Energy Storage Co., Ltd.) to complete the pre-project preparation, construction coordination, safety and quality management, so as to ensure the smooth progress of the project. At present, the project has entered the equipment commissioning stage.
With a total capacity of 30 MW/30 MWh, the project has been under construction since September 2021 and is expected to begin trial operation by the end of March 2022. After being completed, the project can improve the ancillary service response for frequency regulation, make up for the shortcomings of thermal power units in regulation response, and help generating units gain benefits in the ancillary service market.